The foundation is set at NASA’s Kennedy Space Center in Florida for launching crewed missions aboard the agency’s larger and more powerful SLS

. On May 9, 2024, teams with NASA’s EGS (Exploration Ground Systems) Program and contractor Bechtel National Inc.

“Seeing mobile launcher 2 take shape has been incredible,” said Shawn Quinn, program manager for NASA’s EGS Program. “

It is also inspiring for the future of Artemis, with each bolt and truss put in place signifying the next phase of humanity’s return to the Moon.”

In a statement Friday, Nehls said he refused to cooperate with the Office of Congressional Ethics because it was created in 2008 by then-House Speaker Nancy Pelosi.

Teams at Bechtel fabricated temporary pedestals 8 feet off the ground, facilitating a much more efficient and safer initial steel build process by sitting lower to the ground.

Four self-propelled modular transporters were driven underneath the sides of the steel assembly and then lowered the base onto eight surrounding jacks.

“The jack & set milestone is a huge accomplishment for the NASA and Bechtel team,” said Darrell Foster, ground systems integration manager for NASA’s EGS Program.